Brumbaugh Water Main

Project Description

Crews will construct approximately 2,300 feet of an 8-inch ductile iron water main, replacing the existing asbestos cement water mains located within the following areas:

  • 326th Avenue NE
  • 327th Avenue NE
  • NE 47th Street
  • 325th Avenue NE
  • Parts of Milwaukee Avenue.

Work shall include, but is not limited to, replacement and relocation of the existing water main, connection to existing water services, replacement of fire hydrants and valves, connections to the existing system, general restoration, and asphalt paving. Estimated project length is 80 working days.

Project Updates

We patched the trenches that were created for the water lines on 326th and 327th. Trench patching brings things up to the consistent grade and will be a great base layer for the overlay!

Tomorrow they will complete the full overlay on 326th and 327th. If time allows, they will also overlay the 50th intersection this week! Wednesday October 2nd the team will grind and overlay 47th and a one road in the Mobile Haven Park. You will see them raising the utility access holes in the road next week once the road is fully paved.  Once these items are complete, the construction team has hit their substantial completion mark. Most of their equipment will be off-site by the end of the next week. The construction team will be periodically on site finishing up a few remaining items and completing the final punch list for this project.

08/14/2024: Welcome back! With the main water tie ins and all the planned shut-offs the team moved to door hanger notification for immediate notification for residents. All final tie ins to our water system have been complete. Meters have been installed. We are working on 47th Ave installing a water meter vaults. Final restorations and paving will be completed the end of this month. We will give notice for any parking issues. We also have received feedback about the dust/dirt on the site. We will work with the project team to eliminate this as much as possible. Thank you

07/16/2024: The Project Team is still working on replacing and relocating water meters. At the end of the week we will be tying into our main water system. Residents will be notified if there is any water shut off planned.

06/21/2024: Next week the Project Team will be starting on water services and relocate the meter boxes on some residential properties. If you are one of the residents, the contractor will knock on your door before entering your property. Thank you and pardon our dust!

05/31/2024- The Project Team will be finishing working on the east side of 326th street. If your driveway will be blocked, they will knock on your door to make sure you are not blocked in. After that is complete, they will start installing and relocating water service meters for each household. They will give you a heads up before working in front of your house. Thank you and pardon our dust

05/24/2024 - The Project Team will be off site on Monday the 22nd for the observance of the Holiday. They will start back up on Tuesday the 28th. The plan is to head down 326th street work the east side of the street in the City's right of way. Door hangers will be delivered to notify residents. We are asking for any cars to be moved, but anything small the team can get it out of the way.  If your driveway will be blocked, they will knock on your door to make sure you are not blocked in. Pardon our dust!

05/17/2024: The Project Team will be out there starting on Monday working on 327th on the east side of the street. We asked for any cars to be moved, but anything small the project team can get it out of the way. If your driveway will be blocked, they will knock on your door to make sure you will not be blocked in. We are excited to kick off this project. Pardon our dust!

05/10/2024: Project kick off!! Residents received door hangers to let them know the project is starting next week. Project team will be bringing equipment on site. More to come next week! Pardon our dust!

Brumbaugh Water Main Documents